 Day 7 finds the concrete contractor and his crew building the forms for the foundation footings.  



The foundation doesn't actually drop down in front; that's where the 4' frost wall will be.  

 

Day 8

The forms are set and the concrete truck has arrived!  Holy smokes, the divots that truck put in the lawn are insane.  You would think after all these years the soil around the house would be quite compacted, but I guess you don't know exactly how compacted until you have a massive truck weighing a couple tons drive over your lawn.  





Once that's set up and cured, they'll start putting up the wall forms.


Busy times here at Stoneridge Farm!