Monday, November 30, 2020

...trenchin'.

 Day 20 of construction started frosty and clear, and despite a predicted rain and wind storm, this happened:






Because, why not?

This is the trench for the underground electric lines.  I'm so excited - no more wires hanging across my mom's front yard!  The electric lines will come from the pole at the big barn to my part of the house, and from there feed into the existing house and new addition.  We didn't expect the digging to go so easily given that the front yard is mostly ledge, but apparently over the years most of the rock around here has "rotted" and is not as formidable as it once was.

Right now we are experiencing 40 mph wind gusts and torrential downpours, so it's not so much an electric trench as it is a moat. It will be interesting to see what it looks like in the morning.

Sunday, November 29, 2020

Catching Up

 Days 17, 18, and 19.  Between pouring rain and the Thanksgiving holiday, not much to report other than the leach field going in and the sub flooring getting started.  





I like the rock retaining walls the excavating contractor built, but honestly, I'm not thrilled about the placement of the driveway.  I expected it to be more centered and not nearly that close to the mule paddock.  I've decided to live with it for a year and decide if I'm going to have it moved. 






The leach field was not what I was expecting, either.  I was told by the septic designer it would be farther from the house, in a natural depression.  It ended up being right behind the back of my house, basically at the end of where the deck will be.  It's not a big deal, because I did some research and I can still plant over the area, I just can't do raised gardens.  






I also wasn't too thrilled about the septic vent being right in the middle of the back yard.  I did some online searching and found a number of decorative pipe covers, but they were all over $200.  I settled on a cute solar light that mounts on the end of the pipe; it was the most budget friendly and I actually like the look of it.  Once there are plants around it, you'll never know it's actually a stink pipe.

The state inspector should be out to approve the septic system tomorrow, then the excavating contractor can cover it, and move on to digging the trench for the underground electric wires in the front yard.  

We're in for a doozie of a rain and wind storm for the next couple days, so once again it looks like things will be at a standstill for a while. 




Monday, November 23, 2020

Before the rain

 Day 16 - floor joists are going up, more backfilling is happening, and the excavating contractor has started building the retaining wall with those massive boulders he dug up.  








The forecast calls for rain on and off for most of the upcoming week, so I'm not sure how much will get done.  We've been extremely lucky to have had mild weather this late into the season, and I hope it continues for a little while longer.  Just until the garage floor is poured, at least!


Saturday, November 21, 2020

My Own Private Island

 So I made the happy mistake of checking the local Habitat ReStore Facebook page, and of course I saw something I couldn't resist.  

What's a Habitat ReStore?  It's a home thrifter's dream come true, that's what it is!  When people renovate their homes, they donate usable materials, furniture, appliances, decor, and whatnot to Habitat for Humanity.  HFH then sells these items at an amazing discount to the public, and they in turn use the proceeds to fund their projects.  It's a win-win deal!  ReStores are all over the place, so if you love bargain hunting, I highly recommend checking one out.

The treasure I found was this kitchen island:


I want butcher block countertops in my kitchen, so this will fit in perfectly.  I'll paint the base white, of course, and there are a few other details I need to address.  It seems this was a display counter in a retail store originally, and it's not even attached anywhere.  The legs are actually a fraction of an inch short and the countertop doesn't even touch them.  One side of the base was meant to attach to a wall, so it's not finished.  The top is actually upside down in this photo; the other side has a company name and logo carved into it.  I plan to put a small section of beadboard on the unfinished side of the base, and I'll need to give the bottom of the countertop a light sanding then hit it with a few coats of polyurethane so I can use it as the top.  One of the edges also needs to be slightly beveled to match the rest.  Having it in 3 pieces is actually going to make refinishing it that much easier, and it's a perfect size, so I'm incredibly happy to have stumbled across it. 

As far as the house goes, Day 15 was more framing and driveway work.  Apparently there's a discrepancy in the septic plans with the leach field, so they're waiting for the septic designer to come out and go over it before they actually start installing that part.  

Another materials delivery...





I also have an update on the solar light I put in the barn.  It came on automatically at 4:51pm last night.  I think the solar panel has a sensor that kicks on at a certain level of darkness, because it doesn't have a timer and it's dark inside the stall all day, but the light didn't come on at any other time.  Unfortunately when it comes on, it doesn't remember the level of brightness it was set to previously - it just goes straight to the brightest setting.  So long as I'm in the barn to adjust it, that isn't a huge deal.

Here it is from the alley looking into the stalls.


That's a pretty bright light for something so small!  

Here it is on the brightest setting, then the most dim setting.




I'm really pleased with it.  I think I'll move it to the other side of the stall, though, so it shines more into the first stall to give me a little extra light in there.  It didn't look like the mules spent any more time or actually bed down in that back stall with the light on, but they did walk around in it during the night.  That's encouraging.  


Friday, November 20, 2020

Framing

 Hard to believe it's only been two weeks of activity - Day 14 is the day framing has begun!  The backfilling isn't finished, but he's been picking away at it.  It was a little bit of a shock to walk into the dining room and see this out the window:


I was very excited to see this happening; the contractor setting up for a little framing work.


And at the end of the day, the wall was framed.  You can see (barely; it was late!) the garage door, the "man door", and the window.  




I was late taking photos today because I was occupied with setting up a solar night light in Flea's stall.  I've put up the barrier wall between the stall and the run in for the winter, and closed up the little front window.  This makes that a very dark area, and I think the mules are hesitant to go in there because they don't have a good sight line in case of danger.  The stall has been open for nearly 3 weeks now and they hardly ever go in it.  I'm hoping adding a little light might encourage them to use this stall, as it's the most closed in, insulated part of the barn.  

I purchased a hanging solar light from Amazon.  I'm really impressed with how bright it was after only charging for about 6 hours on a cloudy day.  It has a dimming option, which is perfect.  When I'm done inside, I can turn down the brightness with the included remote so it's a softer light.  The mules don't need full on bright light, and this feature was the key reason I chose this setup.  I put the solar panel on the outside and ran the cord through the window, then hung the lamp part from the ceiling.  There's also an option for how long you want it to stay on, and I chose the longest duration.  It should shut off automatically in the early hours after midnight and re-charge during the day.  I'm so impressed with this lamp that I may buy a few more to have on hand for the back yard.  For now, it's a help to have it inside until I have my power back.


Thursday, November 19, 2020

The beat goes on

 Today was all about the foundation.  The general contractor put a waterproofing sealant around the outside of the walls, worked on piping that will run under the connecting room, and the excavating contractor backfilled the front wall of the basement.  Once that was filled and compacted, stone was laid on top of it and leveled.  Eventually a cement floor will be poured, but the foundation needs to be capped before that can happen.  The first delivery of building materials arrived, too.  

Day 13









I'm finally starting to get a feel for the size of the overall house, especially the basement. The garage will be a little more than half the space, and the remaining space will be split into two small rooms.  Since I'll mostly be coming into the house from the basement, the first room I walk into from the garage will be a mudroom and it's a little smaller than I had imagined it.  I'm not disappointed, though; I think it will be more than large enough.  

I'm really looking forward to the driveway being finished, and I hope that happens next.  The electric wires for the new barn run underground near the house site, so they pulled them to ensure they didn't rip them up accidentally.  I've been without power in the barn for a few weeks now, and with the shorter days and colder temperatures, it's been a little inconvenient.  Last night temperatures dipped into the teens, so I had multiple extension cords running from the old shed to the new barn to run the heated water bucket for the mules.  Not the most safe option, but luckily the temperatures look to be heading up for the next week and I shouldn't have to run the heated bucket again for some time.  I have a solar light coming that I'm hoping should light up Flea's stall and work better than my little headlamp.  I'll have to affix the little solar panel to the barn exterior and run the power cord in through the window, then affix the light to the interior wall.  This little hiccup has me rethinking my original barn design, and I may ask my son-in-law if he can put in a larger window in that wall sometime in the future.  Hindsight, you know.

Wednesday, November 18, 2020

And like that *poof*, they were gone.

 Apparently the cement walls only needed to cure overnight, because the concrete crew was back in the morning on Day 12.  Within a few hours they had the forms down, the equipment loaded on the truck, and the site cleaned up.  They did a fantastic job!


photo courtesy Mom





While all of this was going on, my farrier came to trim Flea.  There were trucks and cranes and bangs and booms, but Flea was only his normal turd self, and didn't give Kaitlyn too much of a hard time.  Desensitizing at it's finest; there are people who would pay to put their horses through something like this, ha!

Now the excavating contractor can finish his part of the job.  He will backfill the foundation, put in the new leach field, and has already begun to level off the area for the new driveway.






Mom and I are both floored by the dirt he's digging up right now.  Nary a rock to be seen!  It's definitely better soil than what he dug up for the foundation hole, and what was dug up for the new barn.  I'm sure he'll use this nicer earth to backfill, which means I may actually have a shot at creating some gardens around the edge of the house.  Nice!